Arctic Security Cutter program

The Arctic Security Cutter (ASC) program is an ongoing program to recapitalize the United States Coast Guard's ageing fleet of polar icebreakers with the construction of up to 11 new icebreakers in Finland and the United States.

Last revised
Jun 6, 2026
Read time
≈ 11 min
Length
2,493 w
Citations
45
Source
Class overview
Builders
OperatorsUnited States Coast Guard
Preceded byPolar Security Cutter program
In service2028– (planned)
Planned11
On order
  • 6 (first series)
  • 5 (second series)
General characteristics (first series)1
Displacement8,900 long tons (9,000 t)
Length328 ft (100 m)
Beam67 ft (20 m)
Draft21 ft (6.4 m)
Ice classPolar Class 4
Installed power10,100 kW (13,500 hp)
PropulsionDiesel-electric; 7,200 kW (9,700 hp)
Speed3 knots (5.6 km/h; 3.5 mph) in 4 ft (1.2 m) ice
Range12,000 nautical miles (22,000 km; 14,000 mi)
General characteristics (second series)2
Displacement8,900 long tons (9,000 t)
Length328 ft (99.9 m)
Beam69 ft (21 m)
Draft23 ft (7 m)
Ice classPolar Class 3
Installed power21,000 kW (28,000 hp)
PropulsionDiesel-electric; two 6.5 MW azimuth thrusters
Speed
  • 16 knots (30 km/h; 18 mph) (maximum)
  • 3 knots (5.6 km/h; 3.5 mph) in 4.9 ft (1.5 m) ice
Range
  • Over 12,000 nautical miles (22,000 km; 14,000 mi) (maximum)
  • 6,500 nautical miles (12,000 km; 7,500 mi) at 12 knots (22 km/h; 14 mph)

The Arctic Security Cutter (ASC) program is an ongoing program to recapitalize the United States Coast Guard's ageing fleet of polar icebreakers with the construction of up to 11 new icebreakers in Finland and the United States.

Project timeline

In 2007, the Transportation Research Board and National Research Council report Polar Icebreakers in a Changing World: An Assessment of U.S. Needs concluded that meeting the future polar icebreaking needs of the United States would require a minimum of three multi-mission and one single-mission icebreakers. At the time, the United States had two heavy icebreakers (USCGC Polar Star and USCGC Polar Sea) and one medium icebreaker (USCGC Healy) operated by the United States Coast Guard, and one dedicated icebreaking research vessel operated by the National Science Foundation (Nathaniel B. Palmer). The heavy icebreakers were identified as being at the end of their service life and USCGC Polar Star had been placed in caretaker status.3

The 2010 High Latitude Mission Analysis Report further iterated that the United States Coast Guard would require three heavy and three medium icebreakers to perform its statutory missions in the polar regions.4note 1 In the same year, USCGC Polar Sea became inoperable following an unexpected engine casualty,5 leaving the service without an operational heavy icebreaker and forcing it to charter foreign vessels for Operation Deep Freeze until USCGC Polar Star returned to service following a refit in 2013.6

In 2012, the United States Coast Guard launched an acquisition program for heavy polar icebreakers that, in 2018, were renamed Polar Security Cutters (PSC).78 The detail design and construction of the lead ship was awarded to the Mississippi-based VT Halter Marine on 23 April 2019 with delivery originally planned in 2024.9 As of 2026, the program has been severely delayed with the first vessel, USCGC Polar Sentinel, now expected to be delivered no earlier than 2030.4 As a stopgap measure, the United States Coast Guard acquired the commercial icebreaking anchor handling tug supply (AHTS) vessel Aiviq and commissioned it as the medium icebreaker USCGC Storis in August 2025.10

With the procurement of the Polar Security Cutters underway, the focus shifted to medium icebreakers that, at least since 2020, had been tentatively referred to as Arctic Security Cutters (ASC).11 The 2023 Coast Guard Fleet Mix Analysis increased the size of the fleet required to carry out the United States Coast Guard's Arctic and Antarctic missions in the coming years from earlier six to a total of eight to nine vessels, including four to five heavy and four to five medium icebreakers.4

On 11 July 2024, the United States formed the Icebreaker Collaboration Effort (ICE Pact) with Finland and Canada to collaborate on the development and construction of polar icebreakers.12 However, despite the trilateral partnership, the potential construction of icebreakers for the United States Coast Guard in foreign shipyards would still require presidential waivers to two laws explicitly forbidding this, Title 14 U.S. Code §1151 and Title 10 U.S. Code §8679.4note 2

On 11 April 2025, the United States Coast Guard released a Request for Information (RFI) as part of a market research to assess the capabilities of domestic and foreign shipbuilding industries to support the procurement of Arctic Security Cutters with particular focus on production-ready vessel designs that could be launched within 36 months of contract award.413 In response to this, three Canadian shipbuilders displayed their candidate designs for the Arctic Security Cutter in the CANSEC 2025 defence and security trade show in May: Irving Shipbuilding the Arctic and Offshore Patrol Vessel (AOPS) already being built for the Royal Canadian Navy and the Canadian Coast Guard, Seaspan Vancouver Shipyards the Multi-Purpose Icebreaker (MPI) design developed for the Canadian Coast Guard, and Davie Shipbuilding a new Multi-Purpose Polar Support Ship (MPPS) based on the series of icebreaking offshore vessels built by Helsinki Shipyard in Finland.14

In June 2025, the Davie Shipbuilding announced its plans to acquire Gulf Copper & Manufacturing Corporation's shipbuilding facilities in Port Arthur and Galveston, Texas, and transform them to shipyards that could build Arctic Security Cutters in the United States.15 This announcement followed the company's previous statement, issued in the wake of signing the ICE Pact, that Davie intended to create a permanent shipbuilding presence in the United States.16

On 3 July 2025, the 119th United States Congress passed and, on the following day, President Donald Trump signed into the law the One Big Beautiful Bill Act which included a major recapitalization of the United States Coast Guard icebreaker fleet. The $25 billion total investment includes nearly $9 billion funding for an estimated 17 new icebreakers including Polar Security Cutters and Arctic Security Cutters as well as light and medium domestic icebreakers.1718

On 29 July 2025, the Mississippi-based Bollinger Shipyards, the Finnish shipbuilder Rauma Marine Constructions, and the Canadian Seaspan Vancouver Shipyards announced a strategic trilateral international partnership to offer the Multi-Purpose Icebreaker design originally developed for the Canadian Coast Guard as the future Arctic Security Cutter for the United States. The production-ready design, developed by Seaspan together with the Finnish icebreaker designer Aker Arctic, would be offered with delivery of first vessel within 36 months of contract award and with gradual transition of production to American shipyards.192021

On 8 October 2025, President Trump issued a memorandum enabling the United States Coast Guard to contract the construction of up to four Arctic Security Cutters to foreign shipyards in the interest of national security interest of the United States.22 On the following day, President Alexander Stubb and Prime Minister Petteri Orpo signed a memorandum of understanding on icebreaker collaboration during a working visit to the White House.23 The construction of four of the eleven planned Arctic Security Cutters in Finland was confirmed on the following day.24

On 29 December 2025, the United States Coast Guard awarded the construction of up to six Arctic Security Cutters to two shipyards. The first two icebreakers would be built by the Finnish shipbuilder Rauma Marine Constructions in Finland and the following four by Bollinger Shipyards in the United States with deliveries starting in 2028 and 2029, respectively.252627

On 11 February 2026, the construction of the remaining five Arctic Security Cutters was awarded to Davie Defense, the U.S. subsidiary of the Canadian shipbuilder Davie Shipbuilding,28 who would build two vessels at Helsinki Shipyard in Finland and three at the company's recently-acquired shipbuilding facilities in Texas.2930 The first vessel built under the $3.5 billion contract is scheduled to be delivered in 2028 and all five by February 2035.31

In April 2026, the United States Coast Guard announced that the first two Arctic Security Cutters would be homeported in Alaska.32

Design

First series

3D rendering of the future Arctic Security Cutters built by Rauma Marine Constructions and Bollinger Shipyards. source ↗

The six Arctic Security Cutters contracted to Rauma Marine Constructions and Bollinger Shipyards will be based on the Multi-Purpose Icebreaker design originally developed for the Canadian Coast Guard.2627

The 8,900-long-ton (9,000 t) vessels will be 328 feet (100 m) long overall and have a beam of 67 feet (20 m) and draft of 21 feet (6.4 m). Their hulls will be strengthened to Polar Class 4 in accordance with Lloyd's Register requirements. The vessels will feature diesel-electric power plants with an installed power of 10,100 kilowatts (13,500 hp) and propulsion power of 7,200 kilowatts (9,700 hp), giving them capability to break 3.3-foot (1 m) ice at a continuous speed of 4 knots (7.4 km/h; 4.6 mph). They will have a range of 12,000 nautical miles (22,000 km; 14,000 mi).1

Second series

3D rendering of the future Arctic Security Cutters built by Davie Defense. source ↗

The five Arctic Security Cutters contracted to Davie Defense will be based on the Multi-Purpose Polar Support Ship (MPPS-100) design developed by Helsinki Shipyard based on a series of icebreaking offshore vessels.2

The Polar Class 3 vessels, displacing about 8,900 long tons (9,000 t) at a normal operating draft of 23 feet (7 m), will be 328 feet (99.9 m) long and have a beam of 69 feet (21 m). The diesel-electric power plants will have an installed power of 21,000 kilowatts (28,000 hp) and the vessels will be propelled by two 6,500-kilowatt (8,700 hp) azimuth thrusters giving them a maximum speed of 16 knots (30 km/h; 18 mph) in open water and 3 knots (5.6 km/h; 3.5 mph) in 4.9-foot (1.5 m) ice. Their operational range will be over 12,000 nautical miles (22,000 km; 14,000 mi) in high endurance deep-draft configuration and 6,500 nautical miles (12,000 km; 7,500 mi) at 12 knots (22 km/h; 14 mph) in normal operating mode.2

Ships in class

First series

Name Hull Number IMO number Builder Laid down Launched Delivered Commissioned Homeport Status
115857933 Rauma Marine Constructions (Finland) 2028 (planned) Ordered
115858134 Rauma Marine Constructions (Finland) 2028 (planned) Ordered
Bollinger Shipyards (United States) Ordered
Bollinger Shipyards (United States) Ordered
Bollinger Shipyards (United States) Ordered
Bollinger Shipyards (United States) Ordered

Second series

Name Hull Number IMO number Builder Laid down Launched Delivered Commissioned Homeport Status
4777285 Helsinki Shipyard (Finland) 2028 (planned) Ordered
4777297 Helsinki Shipyard (Finland) 2029 (planned) Ordered
4777302 Davie Defense (United States) 2030 (planned) Ordered
4777314 Davie Defense (United States) 2033 (planned) Ordered
4777326 Davie Defense (United States) 2035 (planned) Ordered
Notes

Notes

  1. In U.S. parlance, "heavy icebreakers" are icebreakers capable of breaking ice up to 6 feet (1.8 m) while "medium icebreakers" can break 4.5-foot (1.4 m) ice.
  2. The Jones Act (Section 27 of the Merchant Marine Act of 1920) applies to commercial vessels carrying "merchandise" between two U.S. ports and is thus not applicable to United States Coast Guard vessels or to vessels engaged in icebreaking operations.
References

References

  1. "Davie Defense awarded ASC deal". The Naval Architect. Royal Institute of Naval Architects. March–April 2026. Retrieved 15 May 2026.
  2. Transportation Research Board and National Research Council (2007), Polar Icebreakers in a Changing World: An Assessment of U.S. Needs, The National Academies Press
  3. O'Rourke, Ronald (21 January 2026), Coast Guard Polar Security Cutter (PSC) and Arctic Security Cutter (ASC) Icebreaker Programs: Background and Issues for Congress, Congressional Research Service, retrieved 15 May 2026
  4. "Engine Troubles Lay Up USCG Cutter Polar Sea". MarineLink. 27 June 2010. Retrieved 15 May 2026.
  5. "USCGC Polar Star Departs for Antarctica Resupply". Defense Media Network. 2 December 2014. Retrieved 16 May 2026.
  6. United States Government Accountability Office (2018), Coast Guard Acquisitions: Status of Coast Guard's Heavy Polar Icebreaker Acquisition, retrieved 16 May 2026
  7. "Coast Guard Renames New Icebreaker Program 'Polar Security Cutter'". USNI News. 27 September 2018. Retrieved 16 May 2026.
  8. "Acquisition update: Coast Guard and Navy Integrated Program Office awards polar security cutter detail design and construction contract". United States Coast Guard. 23 April 2019. Retrieved 16 May 2026.
  9. "Coast Guard commissions its first new icebreaker in more than 25 years". Stars and Stripes. 12 August 2025. Retrieved 16 May 2026.
  10. "The Commandant's Interview", Seapower, Navy League of the United States, July–August 2020, We also are looking to build probably a medium breaker, potentially what we're going to call the Arctic security cutter — a little less capability in terms of icebreaking, but that capability would get us back to being an Atlantic and Pacific icebreaker Coast Guard.
  11. "Biden-Harris Administration Announces New Polar Partnership "Ice Pact" Alongside Finland and Canada". The White House. 11 July 2024. Retrieved 16 May 2026.
  12. "Request for Information - Arctic Security Cutter (ASC): Icebreaking Capable Vessels or Vessel Designs that are Ready for Construction". SAM.gov. 11 April 2025. Retrieved 16 May 2026.
  13. "ICE Pact Lurches to Life". Canadian Global Affairs Institute. June 2025. Retrieved 16 May 2026.
  14. "Davie Advances American Shipbuilding Expansion with Planned Acquisition of Gulf Copper's Texas Shipyards". Davie Shipbuilding. 11 June 2025. Retrieved 16 May 2026.
  15. "Davie intends to create U.S. shipbuilding presence in alignment with ICE Pact". Davie Shipbuilding. 29 July 2024. Retrieved 16 May 2026.
  16. {{cite web|url=https://www.news.uscg.mil/Press-Releases/Article/4235481/us-coast-guard-receives-historic-investment-to-rebuild-under-president-trumps-o/%7Ctitle=U.S. Coast Guard receives historic investment to rebuild under President Trump’s One Big Beautiful Bill|website=USNI News|date=4 July 2025|accessdate=16 May 2026
  17. "Fact Sheet: President Donald J. Trump Authorizes Construction of Arctic Security Cutters". The White House. 9 October 2025. Retrieved 16 May 2026.
  18. "Bollinger to Lead Strategic Trilateral Partnership with American Allies to Deliver U.S. Coast Guard's Arctic Security Cutter". Bollinger Shipyards. 29 July 2025. Retrieved 16 May 2025.
  19. "RMC Joins Strategic Partnership in U.S. Icebreaker Program". Rauma Marine Constructions. 29 July 2025. Retrieved 16 May 2026.
  20. "Seaspan Announces Strategic Trilateral Partnership with American and Finnish Allies to Deliver U.S. Coast Guard's Arctic Security Cutter". Seaspan. 29 July 2026. Retrieved 16 May 2026.
  21. "Construction of Arctic Security Cutters". 8 October 2025. Retrieved 16 May 2025.
  22. "Working visit to Washington D.C. on 9 October 2025". President of the Republic of Finland. 9 December 2025. Retrieved 16 May 2025.
  23. "Suomi ja Yhdysvallat tiivistävät jäänmurtajayhteistyötä". Valtioneuvosto (in Finnish). 10 October 2025. Retrieved 16 May 2026.
  24. "Coast Guard awards contracts to build Arctic Security Cutters". United States Coast Guard. 29 December 2025. Retrieved 16 May 2026.
  25. "RMC awarded contract to build two U.S. Coast Guard Arctic Security Cutters". Rauma Marine Constructions. 29 December 2025. Retrieved 16 May 2026.
  26. "Bollinger Shipyards signs contract to build four U.S. Coast Guard Arctic Security Cutters". Bollinger Shipyards. 29 December 2025. Retrieved 16 May 2026.
  27. "U.S. Coast Guard completes the President's contract awards for 11 Arctic Security Cutters". United States Coast Guard. 11 February 2026. Retrieved 16 May 2026.
  28. "Media Release: Davie Defense Awarded U.S. Coast Guard Contract to Build Five Arctic Security Cutters". Helsinki Shipyard. 11 February 2026. Retrieved 16 May 2026.
  29. "Davie Defense Closes Gulf Copper Acquisition, Confirming U.S. Shipbuilding Expansion". Davie Shipbuilding. 2 December 2025. Retrieved 16 May 2026.
  30. "Coast Guard Finalizes Contract for Five New Arctic Security Cutters". Department of Homeland Security. 13 May 2026. Retrieved 16 May 2026.
  31. "U.S. Coast Guard announces homeporting of the first two Arctic Security Cutters in Alaska". United States Coast Guard. 16 April 2026. Retrieved 16 May 2026.
  32. "RAUMA 6011 (1158579)". Equasis. Ministry of Ecology, Sustainable Development and Energy. Retrieved 16 May 2026.
  33. "RAUMA 6012 (1158581)". Equasis. Ministry of Ecology, Sustainable Development and Energy. Retrieved 16 May 2026.